The CK-1325 CNC Wood Router Machine Installation Tutorial
The CK-1325 CNC Wood Router Machine Installation Tutorial
- Apr 11, 2026
CATEKCNC's CNC routers support both fully assembled and disassembled shipping. Choosing disassembled shipping can significantly reduce your freight costs, allowing you to acquire high-quality equipment at a much lower total investment.
We understand that many customers may find the setup process daunting upon receiving a disassembled machine. To address this, we have filmed this step-by-step assembly guide using our best-selling Standard 1325 CNC Wood Router as an example.
Please follow the steps in this video to complete the assembly. Once installed, you can refer to our operational tutorial videos to learn how to use the machine. If you encounter any issues during the installation process, please feel free to contact us at any time.
Video Timestamps
00:00 Machine Components Overview
00:14 Installing the Bed Support Beams
01:49 Installing the Worktable
02:30 Installing the Gantry Uprights
02:37 Installing the Hard Limits (Y-axis)
03:55 Installing the Gantry Beam
04:21 Installing the Machine Head
04:36 Installing the Hard Limits (X-axis)
04:46 Installing X-axis Transmission System
05:01 Installing the Spindle Mount and Spindle
06:57 Installing the Y-axis Drive & Transmission System
07:51 Installing the Machine Enclosure
08:57 Installing the Cable Carrier Brackets
09:41 Routing Cables into the Control Cabinet
10:22 Installing the Cable Carrier (Y-axis)
11:28 Installing the Cable Carrier (X-axis)
12:11 Connecting Motor Cables and Lubrication Lines (Y2-axis)
14:13 Connecting the Motor Cable (Z-axis)
15:03 Connecting the Motor Cable (X-axis)
15:36 Connecting Oil Lines to the Manifold
15:58 Installing the Machine Head Enclosure
18:17 Connecting the Water Cooling Lines
18:28 Connecting the Lubrication Lines
18:35 Connecting the Spindle Power Cable
18:50 Installing the Spindle Enclosure
19:41 Installing the Motor Enclosure (Y2-axis)
19:59 Connecting the Main Lubrication Line
20:10 Wiring the Lubrication Pump
21:15 Connecting Motor Cables and Lubrication Lines (Y1-axis)
23:09 Installing the Motor Enclosure (Y1-axis)
23:36 Installing Side Dust Strips
23:48 Final Machine Assembly Showcase